A solar lease can run 25 to 40 years. The decommissioning terms you negotiate before signing will protect your land long after the photovoltaic system is installed.
What Is Solar Farm Decommissioning in Maryland?
For a Maryland landowner hosting a community solar farm, decommissioning is the shutdown, removal, and site restoration that happens when the lease ends or the project stops operating. The project owner, whether the original developer or a later buyer, carries out the work and pays for it. You supply the land, and the owner hands it back cleared and restored.
Several events can start the process on leased land. The lease term may expire without renewal, the array may reach the end of its 25- to 35-year operating life, or the system may suffer damage that won’t be repaired.
Maryland’s solar projects are still young. A Maryland Department of Natural Resources technical review notes that none of the state’s utility-scale projects is expected to retire before about 2035, so the lease you sign today will likely govern the entire life of the project.
Removal isn’t the only outcome. Near the end of the term, a developer may offer to repower the site with newer panels and extend your lease instead.
What Maryland Requires in a Solar Decommissioning Agreement
The decommissioning agreement is a binding commitment between the project owner and the PSC, signed on a standard state form. Public Utilities Article § 7-218 applies to ground-mounted stations larger than 1 MW (AC) that serve community solar, aggregate net metering, or the wholesale market. Rooftop, carport, brownfield, and behind-the-meter systems are exempt. The rule grew out of the 2025 overhaul of Maryland solar permitting, which also set statewide setbacks and screening standards.
Maryland is now standardizing what goes into that form. In April 2026, the PSC opened Case No. 9873 to review a proposed template for 1 to 5 MW projects, the size range covering most community solar farms. Final terms are still under review.
The draft calls for a Maryland-licensed Professional Engineer to prepare or approve the cost estimate. Owners must name the specific recycling and disposal facilities that would accept project materials. Removal must begin within six months after power production ends or the lease terminates, with 30 days’ notice to the PSC and the county.
How Decommissioning Bonds Protect Landowners and Communities
A decommissioning bond guarantees there is money to remove the solar farm, even if the developer goes out of business or walks away. A surety company backs the bond, so money for cleanup exists even if the developer can’t pay. Maryland law caps the bond at 125% of the estimated future removal cost, minus the value of salvageable equipment. The first draft of the 2025 law set the cap at 100%. Lawmakers raised it after county, farm, and conservation groups objected, as one of several amendments to the bill.
Under the PSC’s proposed agreement, the developer must post the bond before construction starts. If cleanup doesn’t happen, the PSC or county can collect on the bond directly. If the project is transferred to a new owner, that owner has 20 days to post equivalent security.
Salvage value affects how large the bond will be. Used panels, steel, and copper can be resold or recycled, which lowers the net cost of removal. Because scrap prices can change over 30 years, the draft counts only 85% of the estimated salvage value. The developer also updates the cost estimate and the bond every five years.
Some counties have their own protections. Caroline County, for example, is listed as a co-beneficiary on bonds for projects within its borders, so the county can also collect if removal isn’t completed.
What Happens to Solar Equipment and the Land When a Project Ends?
Crews remove everything they installed and return the ground to its prior use or a condition you approve. Under the proposed standard agreement, removal covers panels, racking, inverters, fencing, cabling, concrete pads, and every post and piling. Compacted soil gets ripped 12 to 18 inches deep so the field can be tilled again. The owner has 12 months to finish, plus one six-month extension for delays beyond its control.
Steel, aluminum, and copper are readily recycled, and the draft directs owners to maximize panel reuse and recycling while keeping panels out of landfills. Glass and aluminum make up more than 80% of a typical panel by weight.
You can ask in writing to keep access roads or a tree buffer that now serves as a windbreak, subject to county approval. However, the owner does not have to rebuild barns or other structures removed to make room for the array.
The draft treats six straight months without power sales as abandonment unless a good-faith repair is underway. After the owner reports completion, the county inspects within 60 days, and the bond is released once officials sign off.
What Landowners Should Review Before Signing a Maryland Solar Lease
The state bond is payable to Maryland and the county, not to you, so your lease needs its own removal and restoration terms you can enforce directly. Confirm it covers these points.
- The developer and any future owner remove all equipment at their own cost, even if expenses exceed the bond.
- Restoration targets a specific standard, such as tillable farmland, and names below-ground items like pilings and buried cable.
- Assignment language binds every future buyer of the project to the same obligations.
- You decide in writing which roads, fences, or buffers stay.
- A firm deadline applies if the project stops producing power.
Because these terms can outlast you, they also shape how a solar lease fits into your estate plan. Review the full agreement with a Maryland real estate attorney, and work through the key questions to ask before leasing early in negotiations.
Explore Maryland Solar Land Leasing With U.S. Light Energy
U.S. Light Energy (USLE) partners with Maryland landowners to turn underused acreage into decades of stable, passive income through community solar. As project owner, USLE handles feasibility, permitting, interconnection, operations, and the decommissioning duties Maryland assigns to developers, with zero upfront cost to you.
Apply for land leasing today to find out if your property qualifies. U.S. Light Energy is leading the charge for a new generation.
Resources:
- https://mgaleg.maryland.gov/mgawebsite/Legislation/Details/SB0931?ys=2025RS
- https://psc.maryland.gov/
- dnr.maryland.gov/pprp/Documents/Decommissioning-Tech-Memo.pdf
- https://mgaleg.maryland.gov/mgawebsite/Laws/StatuteText?article=gpu§ion=7-218&enactments=false
- https://psc.maryland.gov/news/2026/request-for-comments-on-decommissioning-plan-requirements-9873/
- www.eslc.org/update-renewable-energy-certainty-act-sb931-hb1036/
- https://www.carolinemd.org/DocumentCenter/View/11012/Legisl-Bill-2025-010-Compliance-with-Renewable-Energy-Certainty-Act-003_FINAL
- https://psc.maryland.gov/wp-content/uploads/2026/04/PPRP-Rec_Attachment-A-PPRP-Draft-Decommissioning-Agmt.pdf